Case Study
- Designed the scheme in conjunction with client requirements from the college to ensure the best working environment was created
- BIM led M&E scheme coordinated with the main contractor’s BIM work
- 14 m high atrium saw us use specialist lightweight ductwork
- 2 week time saving by G&H Fabrication building the plant room skid off-site
- Deadline met to ensure the college was operational for the new academic year
Key Facts
- Project Title:
- University Technical College 2, Sheffield
- Location:
- Sheffield
- Client:
- The Sheffield College & Sheffield Hallam University
- Services:
- Mechanical and Electrical design and build
- Contractor:
- Bam Construction
- Value:
- £2.5 million
- Duration:
- 22 weeks
- G&H divisions:
- Building Services and Fabrication