Case Study

  • Designed the scheme in conjunction with client requirements from the college to ensure the best working environment was created
  • BIM led M&E scheme coordinated with the main contractor’s BIM work
  • 14 m high atrium saw us use specialist lightweight ductwork
  • 2 week time saving by G&H Fabrication building the plant room skid off-site
  • Deadline met to ensure the college was operational for the new academic year
building-services fabrication

Key Facts

Project Title:
University Technical College 2, Sheffield
Location:
Sheffield
Client:
The Sheffield College & Sheffield Hallam University
Services:
Mechanical and Electrical design and build
Contractor:
Bam Construction
Value:
£2.5 million
Duration:
22 weeks
G&H divisions:
Building Services and Fabrication