Case Study
- Modern day building services retrofitted in a facility constructed in 1930
- Overcame a mid-programme redesign of the mechanical plant
- 3 weeks extension to overcome the weak roof structure
- Re-used steam generated from the plant room boiler house as the primary heat source
Key Facts
- Project Title:
- University of Leeds: School of Fine Art
- Location:
- Leeds
- Client:
- University of Leeds
- Services:
- Mechanical & Electrical Design
- Contractor:
- Sewell Construction
- Value:
- £1.2 million
- Duration:
- 32 weeks
- G&H divisions:
- Building Services