Case Study

  • Modern day building services retrofitted in a facility constructed in 1930
  • Overcame a mid-programme redesign of the mechanical plant
  • 3 weeks extension to overcome the weak roof structure
  • Re-used steam generated from the plant room boiler house as the primary heat source
building-services

Key Facts

Project Title:
University of Leeds: School of Fine Art
Location:
Leeds
Client:
University of Leeds
Services:
Mechanical & Electrical Design
Contractor:
Sewell Construction
Value:
£1.2 million
Duration:
32 weeks
G&H divisions:
Building Services

Find out more information about this project

Download Case Study