Case Study
- Full M&E design and build
- Met a tight deadline of just five months
- Worked in partnership with the main contractor and client
- Bespoke services to meet office, factory, manufacturing and customer areas
- Existing industrial unit converted into a new centre of excellence
Key Facts
- Project Title:
- Steeper Group new HQ (Leeds)
- Location:
- Leeds
- Client:
- Steeper Group
- Services:
- M&E design and build
- Contractor:
- Sewell Construction
- Value:
- £800,000
- Duration:
- 20 weeks
- G&H divisions:
- Building Services