Case Study

  • 20 megawatt combined heat and power on-site energy generation STOR
  • 80 % of the site's pipework fabricated off-site
  • 10 tonnes of steel and copper works made in our specialist facility
  • 8 eighteen inch stainless steel flue pieces among the large-scale fabrications made and delivered
fabrication

Key Facts

Project Title:
Selby CHP STOR
Location:
Selby, North Yorkshire
Value:
£580,000
Duration:
20 weeks
G&H divisions:
Fabrication

Find out more information about this project

Download Case Study