Case Study

  • FULL fabrication and electrical process engineering
  • 200 m of underground gas pipework installed
  • Total off-site prefabrication
  • Delivery connection and on-site testing
  • Installation defect free
fabrication

Key Facts

Project Title:
Lime Kilns
Client:
Centrica Business Solutions
Services:
20MW containerised generation
Value:
£270,000
Duration:
12 weeks
G&H divisions:
Fabrication