Case Study

  • BIM-led mechanical and electrical design and build
  • Grade II listed building sympathetically refurbished with modern building services
  • Met a tight deadline that was non-negotiable due to ticket sales for theatre productions
  • Plantroom pipework sets manufactured off-site by G&H Fabrication saved time and increased safety
building-services fabrication

Key Facts

Project Title:
Hull New Theatre (BIM-led M&E)
Location:
Hull
Client:
Hull City Council
Services:
BIM-led M&E
Contractor:
Sewell Construction
Value:
£2.4 million
Duration:
52 weeks
G&H divisions:
Building Services and Fabrication