Case Study

  • 75 % of the plant room was made off-site
  • 50 % reduction in the time taken to build, test and install the main plant room
  • Delivered the skid-mounted plant room at the most convenient time for the contract
  • Defect and snag-free installation due to the rigorous testing carried out in our specialist facility
building-services

Key Facts

Project Title:
Don Valley Academy (Sheffield)
Location:
Sheffield
Client:
Oasis Community Learning
Contractor:
BAM Construction
Value:
£125,000
Duration:
8 weeks
G&H divisions:
Building Services