Case Study

  • 2 miles of prefabricated stainless steel pipework
  • 9 metre long pipe bridge fabricated offsite
  • 90 % of the scheme was fabricated offsite
  • 8 weeks to install
  • Rooftop and subterranean working in a live hospital environment
fabrication

Key Facts

Project Title:
Clatterbridge Hospital Cancer Centre CHP
Location:
Wirral
Value:
£480,000
Duration:
12 weeks (four weeks prefab, eight weeks installation onsite)
G&H divisions:
Fabrication

Find out more information about this project

Download Case Study